PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Cost Management
You have been working to create lists of resources needed to complete each activity. Some of these lists turned out to be very long, as you need various materials, equipment and people. You have to coordinate all deliveries so that all ordered materials are delivered as close to the start of an activity as possible. The amount of time and money required for each activity has been identified and analyzed. These efforts will result in the creation of a cost baseline for the project. A senior manager wants to know more about process that produces the cost baseline. What process are we talking about?