Cost Management
The current software project you are managing is to create a document scanner app on mobile. The app is to be used to scan documents into your phone and convert them to PDF format. The budget for the project is $45,000. So far, the design work has been completed by the team. Also, you have reviewed the approval from the technical review team and started the coding part of the project. The management is asking you what you expect the project to cost and you think that the costs you have incurred till now are typical for the rest of the project. After reviewing the current status of the project, you find that AC=$15,000 and EV=$17,500. What is the EAC?