Cost Management
You are working for the biggest supplier of training equipment for drivers that participate in auto racing. You have been assigned to oversee a project to manufacture a new piece of equipment designed to improve reaction, hand-eye coordination and stamina. During the forecasting analysis, you found out that the EAC = $270,000 and you are concerned by the fact that the SPI = 0.75 and CPI = 0.88. What is the most likely reason for this occurrence?