Cost Management
All items included in the cost management plan are:
Level of accuracy required for estimates, rules for measuring team performance and specifications for how estimates should be stated.
Level of accuracy required for estimates, rules for measuring cost performance and specifications for how duration estimates should be stated.
Level of risk required for estimates, rules for measuring cost performance and specifications for how estimates should be stated.
Level of accuracy required for estimates, rules for measuring cost performance and specifications for how estimates should be stated.