lock iconCommunications Management

The project manager is sending out progress and status reports to all stakeholders regularly as per the communications management plan. One of the stakeholders has requested a specific progress report on his team's deliverables. The stakeholder is asking the project manager to send the report as soon as possible. The project manager has to find time to fulfill this unexpected request, even though he is almost fully occupied with different project-related activities. What is the best course of action for the project manager in this situation?