Communications Management
The project manager is requested to regularly send multiple reports to internal and external stakeholders. He has to make sure that he's sending information to specific recipients who need to know this information. Even though the project manager ensures that the information is distributed, he is not concerned with whether it reaches the intended recipient or whether it's understood. Which type of communication method is being used by the project manager?