Communications Management
The project manager is working on a new payroll system development and there have been no complaints. However, this morning a key stakeholder has expressed concern about the lack of relevant information on the project team's deliverables in the project status reports sent out by the project manager. The stakeholder believes that the team has no visibility in the project and he wants the project manager to resolve the issue. What should be the first thing to do for the project manager in this situation?