PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Communications Management
The project manager for the organization is currently managing the logistics innovation project. It has 63 stakeholders in three different time zones. According to the communications model, which one of the following means that communications occur when the project manager communicates with the project team?