PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Communications Management
Julia is a project manager of a large organization. She is managing an international project with stakeholders in four countries: Germany, France, Italy and the USA. In this project, Julia will need to plan for project assumptions and constraints that affect how she and the other project stakeholders will communicate. Which one of the following is an example of a project communication constraint?