PMP Exam Simulator
3h 50m 0s
PMP exam lasts 230min and has 180 questions
Use acceleration to have extra 30m in reserve on exam
Communications Management
Tom was assigned to a project on a new software product. Many requirements of stakeholders were not approved for inclusion in Tom's project. It was not easy for Tom to gain formal approval of the project management plan. There were many meetings the stakeholders held to argue about their requirements. However, finally the project was approved and work began half a year ago. Which of the following would NOT be a good preventive action?