Communications Management
There are 2 stakeholders Robert and Charles who are unhappy about how the project effects their own departments. You are a project manager and you were totally unaware of any issues until you overheard them talking to each other. Robert asked if the project was on time. Charles said that the SPI was 1.05. Robert asked if the project manager was aware about Charles' concern. Charles answered that he wasn't sure. What should you do as a project manager?