You are a project manager in a big company. Currently you are managing a project on the production of waterproof drones and there are 3 stakeholders you need to communicate with. Therefore, you have 6 channels of communication. A new stakeholder has just been added and you need to communicate with him as well. How many channels of communication do you have now?